Argyle and Twin Oaks Roadway and Water Main Improvements

PROJECT SCOPE

This Summer the Village will reconstruct residential roadways, perform drainage improvements, and replace watermain in the Browngate Subdivision.  The Village applied for and was awarded a $600,000 Community Development Block Grant from DuPage County to aide in paying for this project.  The streets included in this project are Argyle Street (Marshall Road to East End) and Twin Oaks Street (Marshall Road to East End).  The project also includes complete curb removal and replacement, complete pavement removal and replacement, driveway apron removal and replacement, drainage improvements, watermain replacement, pavement markings, and landscape restoration within the right-of-way.  The construction activities are generally broken down into three phases:

  • Utility Improvements/Repairs – Necessary repairs and additions are made to drainage structures, storm sewers, and a new watermain will be installed beneath the roadway pavement to replace the existing watermain.  No watermain improvements are proposed on Twin Oaks Street.
  • Roadway Improvements – Removal of the existing roadway pavement, roadway base and curbs & gutters will take place.  New stone roadway base, curb and gutters, and new asphalt roadway will be constructed.  Sidewalk and driveway removal and replacement will be performed as needed to ensure drainage and ADA compliance.  This work is generally limited to one side of the street at a time to allow access to properties.  
  • Restoration – The final phase includes parkway restoration, placement of the final pavement surface layer, and then final pavement markings are placed.  Prior to paving, a tack-coat of fresh oil is applied as an adhesive or bonding between the asphalt layers. Fresh oil signage will be posted in advance to remind motorist to travel slowly on the tack-coat material.  

During construction, traffic will be maintained with daily lane closures and flaggers.  Only the immediate works zone area will be closed during working hours.  The project is expected to be substantially completed by Fall 2025, with final completion and landscape restoration completed by November 2025.

Project Details

Contract Bid Date: February 11,2025, 11:00 A.M
Contract Award Date: February 25, 2025
Project Cost: $1,135,000
Awarded Contractor: Acqua Contractors Corporation
Construction Start Date: Spring 2025
Construction Completion Date: November 2025
Funding Sources: Capital Improvements Fund, Utility Fund, and Grant Funds

Project Contact Information

Village of Bensenville Resident Engineer
Brad Hargett, PE,PLS,CFM Matthew Champine, P.E
Assistant Village Engineer Thomas Engineering Group
Email: bhargett@bensenville.il.us
Email: mattc@thomas-engineering.com
Phone: 630-594-3411 Phone: 248-756-2626

Project Documents

Name Link to Document
As-Read Bid Results 02.11.2025 View
Information Letter 1 - Start of Construction View
   

Project Updates


09.25.2025
This week, 1st Choice Landscaping was on site to complete the landscape restoration throughout the project.  Brothers Asphalt was on site last Saturday to complete the asphalt surface course on Argyle Street. Pavement markings are also completed on both Twin Oaks and Argyle. The project is now substantially complete with minor punch list items to finish prior to the final project completion date of October 17, 2025. 

09.05.2025
Acqua Contractors was on site finishing rough grading in preparation of landscape restoration. They also adjusted a utility structure in the pavement prior to paving surface course on Argyle. Next week, 1st Choice Landscaping will be on site to finish the landscape restoration throughout the project. Brothers Asphalt anticipates placing surface course on Argyle Street the week of September 15.

08.29.2025
This week, Acqua Contractors were on site Friday to perform excavation in preparation for landscape restoration. Landscape restoration is anticipated to commence September 8 and be completed by September 15. Placement of the surface course on Argyle Street will follow.

07.18.2025
Brothers Asphalt was on site to place full depth pavement on Argyle Street and surface course on Twin Oaks Street. Surface course on Argyle will be placed following landscape restoration. Landscape restoration will be on hold until weather conditions are favorable for sod to survive, anticipated around first of September. Next week no work is anticipated.

07.11.2025
This week, Impressive Concrete was on site to set bollards and pour new concrete sidewalk at the far east end of Twin Oaks Street.  Brothers Asphalt removed the roadway pavement along Argyle Street and ground the surface course on Twin Oaks. They also paved asphalt driveways along Twin Oaks Street. New week, Brothers Asphalt will place the full depth pavement on Argyle and surface course on Twin Oaks. By the end of next week, the project should be substantially complete with landscape restoration and punch list work remaining.

06.20.2025
Impressive Concrete was on site to continue concrete work along Argyle Street and Twin Oaks Street.  New week, Impressive Concrete will finish with concrete removal and replacements throughout the project. Acqua will perform miscellaneous job site cleanup.

06.13.2025
Impressive Concrete was on site to continue concrete work along Argyle Street. New week, Impressive Concrete with continue with concrete removal and replacements along Argyle Street and start concrete work on Twin Oaks Street.

06.06.2025
Acqua Contractors was on site to perform various jobsite cleanup. The concrete contractor Impressive Concrete began concrete work with concrete removals and pouring new concrete curbs on Argyle Street. New week, Impressive Concrete will continue with concrete removal and replacements along Argyle Street. Work on Twin Oaks Street is expected to commence the week of June 16 with concrete removals.

05.30.2025
Acqua Contractors was on site to complete storm sewer installation along Argyle Street and install storm sewer inlets and storm sewer along Twin Oaks Street. New week the concrete contractor will start concrete improvements with curb and gutter removal and replacement along Argyle Street and Twin Oaks Street. Acqua will perform jobsite cleanup and begin preparing for landscape restoration at offsite storm sewer improvements.  

05.23.2025
Acqua Contractors was on site to continue storm sewer installation and completed transferring water services to the mew water main along Argyle Street. New week, Acqua will finish storm sewer installation and begin roadway excavation.

05.16.2025
This week, Acqua Contractors was on site to continue storm sewer installation and transfer the existing water service to the new water main along Argyle Street. New week, Acqua will finish storm sewer installation. 

05.09.2025
This week, Acqua Contractors was on site commencing with installation of storm between 420 and 434 Country Club Drive then continuing north along the rear yards of 1002 and 1004 Argyle Street. Next week, Acqua will transfer the existing water service to the new water main and continue with storm sewer installation

05.02.2025
Acqua Contractors was on site continuing installation of water main along Argyle Street. They finished the water main installation and pressure tested the water main on Thursday. The landscaper was also on site to finish tree removals. Next week Acqua will start installing the storm sewers. 

04.25.2025
Acqua Contractors was on-site continuing installing water main along Argyle Street. Landscapers were also on-site to begin tree removals for the 36” diameter storm sewer to be installed along the rear yards of 1002 and 1004 Argyle Street. Next week, water main installation and tree removals will continue.

04.18.2025
This week, Acqua Contractors was on site to start construction. Work completed this week include commencing on the water main improvements near Stoneham Street and 1008 Argyle Street. Next week, Acqua will continue installing water main between Stoneham Street and Argyle Street.